MHA Solutions carries out LV power distribution, cable laying and termination, earthing and grounding, and electrical testing and commissioning for industrial plants, healthcare facilities, commercial developments and infrastructure projects across Saudi Arabia. We work as a standalone electrical contractor and as the installation team behind the power systems we supply — which means one contract, one method statement and one party accountable for the finished installation. Most problems on an electrical installation are not caused by the equipment. They happen at the boundaries — between the supplier who provided the switchgear and the contractor who installed it, between the electrical scope and the mechanical scope, between the design drawing and what the site conditions actually allowed. A UPS arrives correctly specified and gets connected to a distribution board that was sized before the load schedule changed. A generator is commissioned but the changeover arrangement was never tested under load because that fell between two contracts. An earthing system is installed to the drawing without anyone measuring the soil resistivity, and the design figure is never achieved. Cable is sized from an ampacity table without applying the derating factors for a duct that runs at 55°C. None of these are exotic failures. They are the ordinary consequences of an installation being delivered in pieces by parties who each did their own scope correctly. We work differently because we can. MHA supplies critical power equipment and holds electrical contracting capability with the same team, so on projects where we do both, the equipment and the installation around it are one scope. Where a client wants us purely as an electrical contractor, that is equally straightforward — we work to the consultant's design and the main contractor's programme like any other subcontractor. What does not change either way is the approach: measure rather than assume, design against the conditions on site rather than a reference table, test everything before energisation, and hand over with documentation that lets somebody else understand what was built.
Cable ampacity tables state how much current a cable can carry under defined reference conditions — a specified ambient temperature, a specified installation method, and a single circuit installed on its own. Real installations rarely match any of those, and Saudi installations frequently match none of them.
The obvious one. A cable run through a roof void, an outdoor duct in direct sun, or an unventilated riser in a Saudi summer is operating well above the reference ambient the table assumed. Its actual current-carrying capacity is correspondingly lower, and the derating factor has to be applied rather than ignored.
The one more often missed. Cables installed together heat each other, so a bunch of circuits on a common tray each carry less than any of them would alone. Where a cable route is heavily loaded, the grouping factor can be substantial.
Applies to buried cables and depends on the soil type and its moisture content. Dry sand conducts heat away from a buried cable considerably less effectively than moist clay, which again reduces the permitted loading.
On long runs this frequently governs the cable size rather than current capacity does. On large industrial sites with long distribution routes, sizing on ampacity alone will produce a cable that is thermally adequate and delivers unacceptable voltage at the far end — which then shows up downstream as motors running hot and equipment misbehaving for reasons nobody connects to the cable.
Finally the cable has to withstand the prospective short-circuit current for the time the protective device takes to clear it, which is a separate calculation again.
We size cable against all of these, state the assumptions used, and record them in the handover documentation. A cable that was sized correctly but for the wrong assumptions is indistinguishable from one that was sized carelessly, until the first hot summer.
Talk to MHA Solutions for expert advice on Power, IT, and Security systems that fit your space. We cover Riyadh, Jeddah, Dammam, and other cities with custom plans.
.png)
Main distribution boards, sub-main boards, final distribution and motor control centres — supply, installation, termination and energisation. The part of this that matters most is rarely on the drawing: protection coordination. A distribution system where the protective devices are not properly discriminated will trip the wrong breaker when a fault occurs, taking out an entire board instead of a single circuit. We check discrimination against the actual fault levels rather than assuming the design got it right, and we flag it where it did not. We also install busbar trunking systems where the load density or the flexibility requirement makes them a better answer than cable.
Protection coordination checked against actual fault levels
.png)
Power and control cable installation from containment design through to termination and testing — cable tray, ladder, trunking, conduit and underground duct systems, with cable pulled, dressed, glanded and terminated properly. Cable sizing is where a lot of installations quietly go wrong in this country, as covered below. Fire-rated cabling for life-safety circuits is a separate discipline again, with its own installation and support requirements that are frequently misunderstood on site.
Power and control cable
.png)
Design, installation and testing of earthing and bonding systems, including soil resistivity survey, electrode design, installation, and measurement of the achieved earth resistance. Saudi ground conditions make this harder than the textbook suggests. It is one of the most commonly under-specified parts of an electrical installation and one of the few where the consequences are a safety matter rather than an operational one.
Earthing and bonding systems
.png)
Pre-energisation and functional testing to a documented protocol: insulation resistance, continuity of protective conductors, earth fault loop impedance, polarity and phase rotation, residual current device operation, protection relay testing, and functional verification of the completed system. Every test is recorded and issued as a commissioning report suitable for handover.
Documented commissioning report
.png)
Plant and process electrical installation — motor circuits and starters, variable speed drive installation, instrumentation and control wiring, panel building and modification, and electrical work associated with plant shutdowns and turnarounds. Shutdown work in particular is about planning rather than labour. The electrical scope has to be sequenced, isolated, tested and returned to service inside a window that does not move, and that is a different kind of job from new-build installation.
Plant and process electrical installation
.png)
Installation, extension and modification of LV switchgear and distribution equipment, including live working procedures where a shutdown is not possible and safe isolation and lock-off where it is. Board extensions on an occupied building are routine work for us and a common source of problems when done without proper planning.
LV switchgear and distribution equipment
.png)
Scheduled electrical maintenance including thermographic survey under load, connection torque verification, insulation resistance trending, protective device testing and panel inspection. Thermal imaging in particular finds developing problems — a loose termination heating up under load — while they are still a maintenance item rather than a fault. Corrective work covers fault finding, repair and system modification on existing installations.
Scheduled and corrective
.png)
Interior and exterior lighting installation including emergency and escape lighting, small power distribution, and containment. Emergency lighting carries its own testing and certification requirements which we handle as part of the works.
Emergency lighting testing and certification
.png)
The installation work around UPS systems, generators, transformers and voltage stabilizers — plant room preparation, cabling and termination, changeover and bypass arrangements, generator synchronisation wiring, fuel system electrics, ventilation interlocks and earthing. This is the work that most often falls between an equipment supplier and a building contractor. We do both, so it does not.
Changeover, bypass and earthing
Plant distribution, motor circuits, drive installation, instrumentation and control wiring, and shutdown and turnaround work delivered inside fixed windows.
Hospital and clinic electrical installation including medical IT systems, separated earthing arrangements, essential and non-essential distribution, and the testing and certification these installations require.
Treatment works and pumping stations, frequently remote, with motor-dominated loads, outdoor installation conditions and earthing in difficult ground.
Hotels, malls, offices and mixed-use developments — distribution, lighting and small power, plant room electrical works and fit-out.
Distribution, containment, earthing and bonding for IT loads, and the electrical works around UPS and generator plant.
Plant electrical installation and maintenance, often to client engineering standards above the national code, with permit-to-work and hazardous area requirements where relevant.
Electrical packages on development and infrastructure projects, delivered to the consultant's design and the main contractor's programme.
An earthing system has one job: to provide a low-impedance path so that protective devices operate quickly during a fault, and so that dangerous voltages do not appear on metalwork people can touch. Everything else about the installation depends on it working.
The difficulty in Saudi Arabia is the ground itself. Earth resistance depends heavily on soil resistivity, and soil resistivity depends heavily on moisture and dissolved salts. Dry sand and rock — which describes a great deal of the Kingdom — have high resistivity, and driving a standard rod into it will frequently produce an earth resistance far above the design target.
It also varies seasonally and with depth. A measurement taken after rain is not representative. A rod that reaches moist ground performs very differently from one that does not, and the depth at which that happens is site-specific.
This is why we survey before we design. A soil resistivity survey using a four-electrode method measures resistivity at several depths, which tells you whether the moisture is at three metres or thirty, and therefore what kind of electrode arrangement will actually work.
From that survey the design follows. Deep-driven rods reaching a lower resistivity layer are usually more effective than multiple shallow rods, and rods spaced too closely interfere with each other and give far less improvement than the count suggests. Where rods alone cannot achieve the target, a horizontal earth mat or ring conductor, conductive backfill material around the electrodes, or a combination of both is normally the answer.
Once installed, we measure the achieved earth resistance using a fall-of-potential method and record the result — because an earthing system designed to a target and never verified is a document rather than a protection.
Beyond the electrode system, the works cover main earthing terminals and equipotential bonding of building services metalwork, interfacing with lightning protection where present, substation earthing including step and touch potential considerations, and separated earthing arrangements where medical IT systems or sensitive electronic installations require them.
Corrosion matters too. Buried connections in coastal soils are subject to accelerated corrosion, so the choice of conductor material, connection method — exothermic welded joints rather than mechanical clamps where the connection will never be accessible again — and any cathodic considerations need addressing at installation, because nobody is digging it up later to check.
An electrical installation is not finished when it is energised. It is finished when it has been tested to a documented protocol, the results are recorded, and somebody who was not there can understand what was built and verify it later.
Our commissioning covers the standard pre-energisation tests — continuity of protective conductors, insulation resistance, polarity, phase rotation and phase sequence, earth fault loop impedance, earth electrode resistance, and residual current device operation and timing. On systems with protective relaying, we carry out secondary injection testing to verify settings and operation.
After energisation we carry out functional testing of the system as built: changeover and bypass operation, interlocks, emergency stops, control sequences and alarm functions. A thermographic survey under load is worth doing at commissioning as well as during maintenance — it identifies loose terminations while the installation team is still on site and the warranty position is straightforward.
Everything is recorded. The handover package covers test results against each circuit, as-built drawings and schedules reflecting what was actually installed rather than what was originally drawn, equipment data and certification, and any deviations from the design with the reason recorded.
That documentation is what the facilities team inherits. It is also what gets consulted the first time something needs modifying, which is usually years later and always under time pressure. An installation with proper records is considerably cheaper to own than one without, and it is one of the clearest indicators of whether a contractor was working to a standard or working to a deadline.
The electrical chapter of the Saudi Building Code is based on the American National Electrical Code rather than on IEC or British Standard practice. That distinction matters more than it might appear, because engineers and contractors arriving from Europe, South Asia and much of the region are trained in a different tradition — different terminology, different cable designations, different protection philosophy, different conductor colour conventions and different installation methods.
The practical consequences on site are familiar to anyone who has worked here: a design drawn to one convention, materials procured to another, and an inspection carried out against a third. Resolving that at inspection stage is expensive; resolving it at design stage costs nothing.
Beyond the building code, several other requirements shape an electrical installation in the Kingdom. The utility has its own connection and metering requirements for supplies it energises. Civil Defence approval applies to fire alarm, emergency lighting and life-safety systems. Product conformity requirements apply to equipment imported into the country. And large clients, particularly in the oil, gas and petrochemical sector, frequently work to their own engineering standards that sit above the national code.
The supply itself differs too. Saudi Arabia operates at 60 Hz, while much of the equipment that arrives on projects here is built for 50 Hz supplies — a mismatch that causes recurring problems with transformers, motors and any equipment containing a magnetic core.
We work to whichever standard the project specifies, and we raise it early where the design, the procurement and the applicable code do not agree with each other. That conversation is always easier before installation than after.
On most projects, critical power equipment and the electrical works around it are bought separately. The UPS or generator comes from an equipment supplier; the distribution, cabling, earthing and changeover arrangements come from an electrical contractor. Each does their own scope competently, and the problems appear where the two meet.
The pattern is consistent. Equipment arrives before the plant room is ready. The distribution board was sized against an earlier version of the load schedule. Ventilation was designed for a smaller unit. The changeover arrangement is installed but never tested under load, because testing it required both parties on site at the same time and nobody owned that. Then something fails, and each party can demonstrate that their own scope was delivered correctly.
We hold both capabilities, so on projects where we supply the equipment we also carry out the installation around it — plant room preparation, ventilation and heat rejection, cabling and termination, protection and discrimination, earthing, bypass and changeover arrangements, and commissioning of the whole thing as one system rather than as a set of parts.
That means one contract, one method statement, one programme, one set of commissioning documentation, and one party responsible when something does not work.
It also works the other way. Where a client already has equipment, or is procuring it elsewhere, we take the electrical scope alone and work to the consultant's design and the main contractor's programme like any other electrical subcontractor. The capability is not conditional on us selling you a UPS.
The equipment side of our work covers UPS systems, diesel generators, transformers, voltage stabilizers, battery systems and load bank testing — all of which are documented in detail elsewhere on this site.
We deliver electrical works Kingdom-wide from our base in Jeddah — Riyadh, Dammam, Khobar, Jubail, Yanbu, Makkah, Madinah, Taif, Abha and remote industrial and infrastructure sites. Installation, testing, commissioning and maintenance are carried out by our own engineers and technicians.
LV power distribution including main and sub-main boards and motor control centres, power and control cable laying and termination with containment, earthing and grounding system design and installation, electrical testing and commissioning, industrial and plant electrical works, switchgear installation and modification, lighting and small power, preventive and corrective maintenance, and the electrical works associated with UPS, generator and transformer installations.
Both. Where we supply power equipment we usually carry out the installation around it as a single scope, which removes the boundary between supplier and contractor. Where a client already has equipment or is procuring it elsewhere, we take the electrical package on its own and work to the consultant's design and the main contractor's programme like any other subcontractor.
The electrical chapter of the Saudi Building Code is based on the American National Electrical Code rather than on IEC or British Standard practice. This regularly causes confusion on projects staffed by engineers trained in the IEC tradition, because terminology, cable designations, protection philosophy and installation methods all differ. Large clients in the oil, gas and petrochemical sector often work to their own engineering standards above the national code, and utility connection requirements and Civil Defence approvals apply in addition.
Earth resistance depends on soil resistivity, and soil resistivity depends heavily on moisture and dissolved salts. Dry sand and rock — which describes much of the Kingdom — have high resistivity, so a standard driven rod frequently produces an earth resistance well above the design target. It also varies seasonally and with depth. This is why we carry out a soil resistivity survey before designing rather than assuming a typical value, and why deep electrodes, earth mats or conductive backfill are often needed rather than simply adding more rods.
Yes, always. We measure the achieved earth resistance using a fall-of-potential method and record the result. An earthing system designed to a target figure and never verified is a drawing, not a protection — and since the electrode system is buried, verification at installation is the only practical opportunity to confirm it.
Ampacity tables assume reference conditions that Saudi installations frequently do not match. We apply derating factors for the actual ambient temperature, for grouping where cables are installed together, and for soil thermal resistivity on buried runs. We also check voltage drop, which on long distribution routes often governs the cable size rather than current capacity, and short-circuit withstand for the clearing time of the upstream device. The assumptions used are stated in the handover documentation.
Discrimination, or selectivity, means that when a fault occurs the protective device closest to it operates and the ones upstream do not. Without it, a fault on a single final circuit can trip an entire distribution board or worse, turning a minor fault into a significant outage. It depends on the characteristics and settings of the devices relative to the fault levels present. We check it against actual fault levels rather than assuming the design accounted for it, and we raise it where it did not.
Often, yes, depending on what the work involves and what isolation is available. Board extensions, additional circuits and much maintenance work can be planned around live sections with proper procedures and isolation. Some work genuinely requires a shutdown, and where it does we plan the sequence to fit the shortest practicable window. Shutdown and turnaround work is a large part of what we do on industrial sites, and the planning matters more than the labour.
Test results recorded against each circuit, as-built drawings and schedules reflecting what was actually installed rather than what was originally drawn, equipment data and certification, commissioning records including functional test results, and any deviations from the design with the reason recorded. This is what the facilities team inherits and what gets consulted the first time something needs modifying.
Yes, under contract or on call. Scheduled maintenance covers thermographic survey under load, connection torque verification, insulation resistance trending, protective device testing and panel inspection. Thermal imaging is the most valuable single item — it finds a termination heating up under load while it is still a maintenance task rather than a fault. We also take on fault finding, repair and modification work on installations we did not build.
Send us the drawings, the specification, or simply a description of the site and what needs doing. We will tell you what the scope realistically involves, where we see risk in the design, and what it will cost — whether that is a full electrical package, a shutdown, or the installation around equipment you have already bought.
Most facilities in the Kingdom deal with separate suppliers for power, IT and security, then discover the gaps between them at the worst possible moment. The UPS vendor points at the electrical contractor. The IT supplier says the rack was never their scope. Nobody owns the problem.
MHA Solutions covers all four disciplines with one engineering team. That means one point of accountability for the UPS, the distribution board feeding it, the server rack it protects and the access control system on the door of the room.
We work with industrial plants, healthcare facilities, government entities, data centres, telecom operators and major infrastructure contractors across Saudi Arabia. Our engineers handle the full lifecycle: site survey and load study, system design and specification, supply, installation, testing and commissioning, and ongoing maintenance under contract.
Equipment that performs well in a temperate climate does not always survive a Saudi plant room. Ambient temperatures above 45°C shorten battery life, airborne dust clogs filters and cooling paths, and salt-laden humidity on the Red Sea coast attacks enclosures and terminations. We specify for those conditions from the start, because replacing equipment early is far more expensive than sizing it correctly on day one.
Discover Our JourneyHappy customers
Brand partnerships
Years in business
Countries Served

Explore engineered solutions for mission-critical environments across power, IT and security.
Engineering reliable infrastructure for critical facilities.
Engineering reliable infrastructure for critical facilities.
Engineering reliable infrastructure for critical facilities.
Engineering reliable infrastructure for critical facilities.